The reconstruction plan is divided into the following stages:
1. Reconstruction of the existing building with a total estimated cost of approximately CZK 34,000,000 (≈ USD 1,400,000, including VAT).
a) Structural stabilization (CZK 2,500,000 / ≈ USD 100,000).
b) Repair of the deteriorated roof structure, including roofing and preparation for the attic conversion (CZK 7,500,000 / ≈ USD 310,000).
c) Remaining works – primarily the construction of a hall, office, kitchen, and sanitary facilities on the ground floor; apartments for priests with guest rooms on the first floor; and eight guest rooms in the attic, including heating, electrical wiring, and sewage systems (CZK 25,000,000 / ≈ USD 1,030,000).
– This part of the project may, if necessary, be divided into smaller sub-stages.
We plan to cover the total budget of CZK 35,000,000 (≈ USD 1,440,000) which is estimated on the basis of the construction documentation, with an estimated CZK 12,000,000 (≈ USD 490,000) from state subsidies and CZK 7,000,000 (≈ USD 285,000) from our own resources. This leaves approximately CZK 16,000,000 (≈ USD 665,000) remaining needed for the complete implementation of the first stage.
(USD values are based on an exchange rate of 1 USD ≈ 24.3 CZK.)